PgMP Practice Question
Which approach uses numerical indicators of activity progress and resource usage to reveal mismatches between actual outcomes and planned levels?
It organizes tasks in evolving phases for gradual definition but lacks an integrated cost-schedule view
It prioritizes investigating reasons behind delays but excludes regular financial considerations
It applies measures to finished work and resource utilization to highlight variances from targets
None of these