Project Management Professional Practice Question

Your project is transitioning into the operation phase and focuses on long-term benefit realization. What is the most crucial action to ensure benefits are continuously realized post-project?

  • You selected this option

    Initially define responsibilities during the project closure phase

  • You selected this option

    Conduct training for all stakeholders on how to measure and report on project benefits

  • You selected this option

    Regularly review the benefits realization plan with the project team

  • You selected this option

    Formally document an agreement specifying who is responsible for the ongoing tracking and reporting of benefits

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot