Your project is progressing well, but you have received feedback indicating that some stakeholders feel uninformed about recent changes. What should be your FIRST step according to best practices in 'Monitor Communications'?
Change the frequency of all regular meetings to more frequent intervals.
Send an email to all stakeholders with all recent project documents attached.
Create a new communication platform for stakeholders to access information independently ad-hoc as required by the individual stakeholder.
Review the communication management plan and stakeholder engagement to validate effectiveness and identify necessary adjustments.