Free PMI Project Management Professional Practice Question

You manage a project team dispersed across multiple time zones and wish to gauge the ongoing effectiveness of your virtual engagement strategies. Which method would be MOST effective for obtaining a detailed assessment of team participation and satisfaction?

  • Monitor the responsiveness to emails within the team as a measure of engagement.

  • Analyze the usage statistics of the implemented virtual tools.

  • Observe active engagement metrics within team collaboration platforms.

  • Implement periodic detailed surveys designed to elicit qualitative feedback about the virtual engagement tools and overall team satisfaction.