PMI Project Management Professional Practice Question

You are managing a software development project when a major stakeholder requests an additional feature. This feature was not included in the original scope and will require additional time and resources to implement. You understand that this change could impact the project's cost, schedule, and scope. What is the BEST initial step you should take according to the PMBOK guide's Perform Integrated Change Control process?

  • Request an increase the project budget and extend the timeline to accommodate the new feature.

  • Evaluate the change request's impact on the project's baselines and overall objectives before deciding to proceed.

  • Reject the change request to avoid any negative impact on the project.

  • Implement the feature as per the major stakeholder's request.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot