You are managing a project that has multiple stakeholders with varying levels of influence and interest in the project. To gain or maintain their support, it is essential to develop a Stakeholder Engagement Plan. Which of the following would BEST serve as the basis for developing your stakeholder engagement strategies?
You selected this option
Past experiences and lessons learned from previous similar projects
You selected this option
An analysis of stakeholders' power, interest, expectations, and potential impact on project success
You selected this option
General communication preferences of the project's stakeholders
You selected this option
The geographical distribution of stakeholders' offices
The best basis for developing stakeholder engagement strategies is a detailed analysis of stakeholders' expectations and potential impact on the project. This analysis will help prioritize stakeholder needs and interests, allowing for the formulation of appropriate engagement strategies. It also aids in the identification of the optimal mix of engagement strategies to address the diverse requirements and concerns of stakeholders
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Stakeholder Engagement Plan?
Open an interactive chat with Bash
What does 'power and interest' analysis involve?
Open an interactive chat with Bash
Why is understanding stakeholder expectations important?
Open an interactive chat with Bash
Project Management Professional
Waterfall
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Oh snap!
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access