Project Management Professional Practice Question

Which of the following is an effective method to confirm that the performance of team members has improved after implementing new processes or training?

  • You selected this option

    Soliciting feedback from team members about their experience

  • You selected this option

    Assessing overall team member satisfaction

  • You selected this option

    Comparing current performance data with the baseline data

  • You selected this option

    Measuring the increase in workload managed by the team

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot