Which of the following best describes the primary purpose of managing suppliers and contracts in a project?

  • You selected this option

    Ensuring the project receives necessary resources and services from external providers while meeting agreed-upon standards

  • You selected this option

    Preventing any changes to the project scope

  • You selected this option

    Minimizing overall project costs

  • You selected this option

    Negotiating the lowest possible prices with suppliers

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot