Project Management Professional Practice Question

What is the value of Expert Judgment in project risk management?

  • You selected this option

    To supplement quantitative risk analysis by incorporating statistical models along with other evaluation techniques.

  • You selected this option

    To expand the project risk register to include a diverse range of potential risks.

  • You selected this option

    It utilizes the specialized insights of experts to enhance risk identification, analysis, and the development of response strategies.

  • You selected this option

    To integrate experts' opinions as part of a broader risk identification and evaluation process.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot