PMI Project Management Professional Practice Question

What is the purpose of continuously reassessing impediments, obstacles, and blockers for the team?

  • To micromanage the team's work and control every aspect of the project

  • To demonstrate the project manager's authority and maintain a hierarchical structure

  • To ensure that the team's progress is not hindered by any persistent or new obstacles

  • To create unnecessary paperwork and burden the team with additional tasks

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot