Project progress is sufficiently achieved by tracking the completion of established milestones.
False
True
Solely tracking the completion of milestones does not provide a sufficiently comprehensive view of project progress. While milestones are important indicators of major achievements, they do not capture day-to-day variations, task dependencies, or qualitative aspects of project execution such as team dynamics and stakeholder satisfaction. It's crucial to employ a more detailed and continuous monitoring approach to truly gauge the health and progress of a project.