In the context of a Waterfall project, a project manager is reassessing the stakeholder engagement plan mid-project due to newly identified risks and stakeholders. Which of the following techniques should the project manager prioritize to reassess current support and devise appropriate strategies for enhanced stakeholder engagement?
Perform a stakeholder analysis to identify stakeholders' needs, expectations, and potential impact on the project.
Focus on stakeholder expectations without consideration of the newly identified risks and changes in stakeholder dynamics.
Delegate to a newly formed team who will focus on stakeholder engagement.
Reduce project communication to a limited number of key stakeholders to streamline decision making.
The project manager should prioritize stakeholder analysis, as it aids in the reassessment of already identified stakeholders and the discovery of new ones. This analysis also provides insight into stakeholders' current levels of support or resistance, informing the project manager of potential impact on the project's success. Effective stakeholder analysis allows for the identification of appropriate engagement strategies for individuals based on their interest, rights, knowledge, and contribution to the project, ensuring that all potential influences are accounted for and managed adequately.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is stakeholder analysis in project management?
Open an interactive chat with Bash
Why is stakeholder analysis critical when new risks and stakeholders are identified?
Open an interactive chat with Bash
How does stakeholder analysis inform engagement strategies?
Open an interactive chat with Bash
Project Management Professional
Waterfall
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .