Project Management Professional Practice Question

During the quantitative risk analysis phase, what does a Decision Tree Analysis primarily help to determine?

  • You selected this option

    It determines the degree of consensus achieved in a Delphi Technique.

  • You selected this option

    It calculates the Expected Monetary Values (EMVs) for different possible scenarios assisting in choosing the optimal decision path.

  • You selected this option

    It identifies the sequence of scheduled activities in the critical path method.

  • You selected this option

    It indicates the interdependencies of project tasks within a Work Breakdown Structure (WBS).

Project Management Professional
Process
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot