During the project closure or transition phase, which of the following is the most important factor to consider when validating readiness for transition?
Verifying that all project team members have transferred their knowledge to the operations team
Ensuring that resources are allocated for the next phase or project
Confirming that all deliverables meet the established acceptance criteria
Obtaining stakeholder approval for the transition plan