Project Management Professional Practice Question

During the execution phase of a project, you notice that the actual costs are exceeding the budgeted costs by 15%. Upon further investigation, you discover that the primary reason for this variance is an unanticipated increase in the cost of raw materials. Which of the following actions should you take to address this budget variation while adhering to the project governance process?

  • You selected this option

    Renegotiate contracts with suppliers to reduce the cost of raw materials without involving the project governance team

  • You selected this option

    Inform the project sponsor of the situation and request additional funding to cover the increased costs

  • You selected this option

    Analyze the impact of the budget variance on the project's overall success and present options to the project steering committee for their decision

  • You selected this option

    Immediately cut discretionary spending in other areas of the project to compensate for the increased cost of raw materials

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot