During the execution phase of a project, a key stakeholder requests a significant change in the project scope. As the project manager, what should be your immediate course of action?

  • You selected this option

    Immediately implement the change to satisfy the key stakeholder

  • You selected this option

    Postpone the decision until the next project phase

  • You selected this option

    Reject the change request to avoid any disruptions to the project plan

  • You selected this option

    Assess the impact of the requested change on the project's objectives, timeline, and budget

Project Management Professional
Process
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot