PMI Project Management Professional Practice Question

During a software development project, a new government regulation has been introduced, requiring additional data security measures. The Project Manager must adapt the project scope to accommodate these changes. Which of the following is the best option to manage the impact on the project's schedule and costs?

  • Increase the project budget to cover additional costs.

  • Limit the scope of existing project features to accommodate the new security changes within the current budget.

  • Conduct a revised cost-benefit analysis to assess the financial impact and adjust the timeline accordingly.

  • Extend the project timeline by estimating the time required for implementing new security measures.

PMI Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot