PMI Project Management Professional Practice Question

During a project review, the project manager notices that the Actual Cost (AC) for a specific work package is higher than expected. What does this indicate about the project's cost performance?

  • The project is behind schedule

  • The project will finish under budget

  • The project is over budget for the work package

  • The project scope has increased