Project Management Professional Practice Question

During a project review, the project manager notices that the Actual Cost (AC) for a specific work package is higher than expected. What does this indicate about the project's cost performance?

  • You selected this option

    The project will finish under budget

  • You selected this option

    The project scope has increased

  • You selected this option

    The project is behind schedule

  • You selected this option

    The project is over budget for the work package

Project Management Professional
Process
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot