PMI Project Management Professional Practice Question
As the project manager for a construction project, a sudden legislative change mandates additional environmental safety measures. Given that these changes are imminent and your current project scope does not include these new measures, what is your most appropriate initial action?
Immediately implement the new safety measures to avoid legal penalties.
Urgently convene a team meeting to discuss the changes without reviewing the legislation details.
Consult with legal experts to oppose the new legislation.
Conduct a detailed review of the legislative changes to understand their specific implications on your project.