Project Management Professional Practice Question

As a project manager, you have established key performance indicators (KPIs) for each team member. During a performance review, you notice that one team member consistently misses their deadlines, resulting in delays in dependent tasks. However, the quality of their work is exceptional. What should you do?

  • You selected this option

    Ignore the missed deadlines and focus on the team member's strengths, as the quality of their work is more important than meeting deadlines.

  • You selected this option

    Schedule a meeting with the team member to discuss their performance against the established KPIs and work together to develop a performance improvement plan.

  • You selected this option

    Praise the team member for their exceptional work quality and do not mention the missed deadlines to avoid demotivating them.

  • You selected this option

    Immediately escalate the situation to the Human Resources department and request that the team member be placed on a performance improvement plan.

Project Management Professional
People
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot