An agile team seeks to enhance their sprint planning by accurately forecasting how much product backlog work they can likely accomplish in the next sprint. Which metric would provide the best foundation for their sprint capacity planning?
Velocity is the key agile metric utilized to gauge how much work an agile team can complete in a sprint, where work is typically measured in story points or other units. It is calculated from historical data of previous sprints. This predictive measure helps teams estimate their future sprint capacity based on past performance, thus proving the most relevant for capacity planning during sprint planning.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
How is velocity calculated in agile?
Open an interactive chat with Bash
Why is a burn-down chart not suitable for sprint capacity planning?
Open an interactive chat with Bash
What is the difference between velocity and a cumulative flow diagram?
Open an interactive chat with Bash
Project Management Professional
Agile
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .