PMI Project Management Professional Practice Question
A project manager is working on a construction project and notices that the resource histogram shows significant peaks and valleys in the workload for skilled laborers. Which technique should the project manager apply to address this issue without changing the project's critical path or completion date?
Resource smoothing
Crashing the schedule
Fast tracking
Resource leveling