A project manager calculates the Schedule Performance Index (SPI) and finds it to be 0.85. What does this value indicate about the project's schedule performance?

  • The project is behind schedule

  • The project is exactly on schedule

  • The project is 85% complete

  • The project is ahead of schedule

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot