PMI Project Management Professional Practice Question

A project is underway when a key stakeholder requests an additional feature, extending the duration of a critical path task by two weeks. The project manager must evaluate the request and take necessary actions to manage the change. What should the project manager do FIRST in response to this situation?

  • Inform the stakeholder that changes cannot be made to tasks on the critical path when following the Waterfall Methodology.

  • Approve the change request to accommodate the stakeholder's need.

  • Evaluate the impact of the new feature on the project's schedule baseline and overall objectives.

  • Reject the change request to maintain the original schedule and prevent any delays.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot