CompTIA Project+ PK0-005 Practice Question
You are a project manager overseeing a long-term project that relies on a critical software tool. The vendor of this software has announced it will reach end-of-life in six months, and support will be discontinued. Your project is scheduled to continue for another year. What is the most appropriate action to take to manage this resource life cycle issue?
Delay addressing the issue since there are still six months before the software support ends.
Assign team members to develop a custom tool internally without assessing needs.
Initiate a needs assessment to determine requirements for a replacement tool and plan for its acquisition.
Continue using the current software tool until the end of the project to maintain consistency.