CompTIA Project+ PK0-005 Practice Question
In a Scrum team, who is responsible for maximizing the value of the product by prioritizing the work items and managing the backlog?
Development Team
Product Owner
Scrum Master
Project Sponsor
In a Scrum team, who is responsible for maximizing the value of the product by prioritizing the work items and managing the backlog?
Development Team
Product Owner
Scrum Master
Project Sponsor
The Product Owner is responsible for maximizing the value of the product by managing the Product Backlog. This involves prioritizing work items based on factors like stakeholder input, business value, and market trends. The Scrum Master facilitates the Scrum processes but does not prioritize work items. The Development Team implements the work but doesn't manage the backlog. The Project Sponsor is typically not a role within the Scrum framework.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Information Technology Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All Information Technology Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.