CompTIA Project+ PK0-005 Practice Question
During the project planning phase, it's acceptable to exclude external audiences from the transition plan because they can be informed later during project execution.
False
True
🏆 Win a Lifetime Membership! Click here to enter.
During the project planning phase, it's acceptable to exclude external audiences from the transition plan because they can be informed later during project execution.
False
True
This statement is false. Excluding external audiences from the transition plan during the planning phase can lead to significant issues. Effective communication with both internal and external stakeholders should be planned ahead of time to ensure all parties are informed and prepared for changes. Including external audiences in the transition plan helps mitigate risks associated with miscommunication and ensures smoother project implementation.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Information Technology Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All Information Technology Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.