CompTIA Project+ PK0-005 Practice Question
During a project involving confidential trade secrets, how should a project manager control access to sensitive information within the team?
Protect documents with passwords and distribute them to team members.
Encourage open sharing of all project information among team members to improve collaboration.
Establish a data classification system to categorize information and assign access permissions.
Provide sensitive data to team members upon request using standard communication methods.