At the conclusion of a project meeting, several team members received new assignments and due dates. What should the project manager do next to formally document and communicate these assignments to the team?

  • You selected this option

    Rely on team members to recall their assignments independently

  • You selected this option

    Update the project schedule and notify team members of the changes

  • You selected this option

    Wait until the next meeting to review the assignments again

  • You selected this option

    Distribute a written summary of the meeting with the assignments and due dates

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot