CompTIA Project+ PK0-005 Practice Question
At the conclusion of a project meeting, several team members received new assignments and due dates. What should the project manager do next to formally document and communicate these assignments to the team?
Rely on team members to recall their assignments independently
Update the project schedule and notify team members of the changes
Wait until the next meeting to review the assignments again
Distribute a written summary of the meeting with the assignments and due dates