CompTIA Project+ PK0-005 Practice Question
As a project manager, you have implemented a new project management software across your organization. After initial training, you notice that some team members are not fully utilizing the new software and are reverting to old methods. Which action should you take to enhance the long-term adoption of the new system?
Implement a policy encouraging the use of the new software with clear expectations.
Monitor team members' adaptation to the new software without immediate intervention.
Gradually phase out access to old methods to promote use of the new software.
Provide ongoing coaching and support to the team members.