CompTIA Project+ PK0-005 Practice Question
As a project manager on a key project experiencing delays, you need to update stakeholders on when the project is now expected to finish. By analyzing current progress and performance data, you aim to determine the new completion date and adjust your project plan accordingly. Which of the following techniques should you use to estimate the project's remaining duration?
Critical Path Analysis
Variance Analysis
Forecasting
Resource Leveling