CompTIA Project+ PK0-005 Practice Question
As a project manager in the planning phase, which of the following should be included in the project plan to ensure that project deliverables are smoothly integrated into the organization's daily operations?
Develop a proposal for future projects
Organize a social event to celebrate project completion
Set up a customer satisfaction survey
Include a plan for staff training on the new deliverables