A project manager opts to use prequalified vendors/sellers during procurement planning. Which of the following is the BEST benefit of this decision?
It speeds up the contracting process by minimizing procurement steps.
It permits flexibility in bypassing standard procurement procedures.
It reduces the project's risk by selecting vendors with proven performance.
It results in lower costs due to existing vendor agreements.