A project manager opts to use prequalified vendors/sellers during procurement planning. Which of the following is the BEST benefit of this decision?
It results in lower costs due to existing vendor agreements.
It speeds up the contracting process by minimizing procurement steps.
It reduces the project's risk by selecting vendors with proven performance.
It permits flexibility in bypassing standard procurement procedures.