CompTIA Project+ PK0-005 Practice Question

A project manager opts to use prequalified vendors/sellers during procurement planning. Which of the following is the BEST benefit of this decision?

  • You selected this option

    It results in lower costs due to existing vendor agreements.

  • You selected this option

    It speeds up the contracting process by minimizing procurement steps.

  • You selected this option

    It reduces the project's risk by selecting vendors with proven performance.

  • You selected this option

    It permits flexibility in bypassing standard procurement procedures.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot