CompTIA Project+ PK0-005 Practice Question
A project manager opts to use prequalified vendors/sellers during procurement planning. Which of the following is the BEST benefit of this decision?
It reduces the project's risk by selecting vendors with proven performance.
It results in lower costs due to existing vendor agreements.
It permits flexibility in bypassing standard procurement procedures.
It speeds up the contracting process by minimizing procurement steps.