CompTIA Project+ PK0-005 Practice Question
A project manager notices that a recurring issue is causing delays in the project schedule. To address the problem permanently, the project manager should perform which of the following activities?
Implement a work-around
Update the project documentation
Escalate the issue to senior management
Conduct a root cause analysis