CompTIA Project+ PK0-005 Practice Question

A project manager needs to inform the team about a minor change in the project schedule due to an unexpected delay in material delivery. The delay does not affect the overall project timeline significantly, but the team needs to adjust their tasks accordingly. What is the BEST way for the project manager to communicate this information to the team?

  • Post the updated schedule on the project collaboration tool and notify the team via an informal chat message.

  • Update the schedule in the project management software without notifying the team.

  • Send an official email with the updated schedule attached.

  • Call a formal meeting with all team members to discuss the change.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot