CompTIA Project+ PK0-005 Practice Question

A company is initiating a project with clear, unchanging requirements and a fixed budget and timeline. Which project management methodology would BEST suit this project?

  • You selected this option

    DevOps

  • You selected this option

    Kanban

  • You selected this option

    Scrum

  • You selected this option

    Waterfall

CompTIA Project+ PK0-005
Project Management Concepts