CompTIA Network+ N10-009 Practice Question
The IT team at a large retail company is reviewing their disaster recovery strategy to align it with the organization's requirement for moderate downtime in event recovery scenarios. They are considering implementing a warm site. Which of the following best describes the state of a warm site that they should expect?
Fully operational with all services, applications, and data mirrored from the primary site running in real-time.
Equipped only with the physical infrastructure and requires all servers, applications, and data to be restored before operations can resume.
Lacks any pre-installed hardware and is primarily an empty data center reserved for emergency use.
Partially equipped with servers, network connections, and possibly some live data feeds, but requires some configuration to become fully operational.