Free CompTIA Network+ N10-009 Practice Question

A company is planning to upgrade its network switches to a new model to enhance performance and security. The network administrator needs to ensure the process aligns with best practices for change management. What is the FIRST action they should take?

  • Create a formal change request.

  • Deploy a pilot change in a small segment of the network.

  • Start with an impact analysis of the current network configuration.

  • Review vendor documentation for the new model.

This question's topic:
CompTIA Network+ N10-009 / 
Network Operations
Your Score: