00:15:00

Free PMI Project Management Professional Practice Test

Prepare for the PMI Project Management Professional exam with this free practice test. Randomly generated and customizable, this test allows you to choose the number of questions.

  • Questions: 15
  • Time: 15 minutes (60 seconds per question)
  • Included Objectives:
    • People
    • Process
    • Business Environment
    • Agile
    • Waterfall
Question 1 of 15

Maintaining a constant monitoring and evaluation of the deliverables' quality throughout the project lifecycle can significantly diminish the potential of project failure.

  • True

  • False

Question 2 of 15

A project manager is preparing to showcase the value derived from the completed phases of a project. Which of the following would be the most effective way to evaluate and demonstrate the incremental value delivered to the stakeholders?

  • Describing the technical specifications of the project deliverables.

  • Listing the project's completed activities and tasks.

  • Comparing project deliverables with the initial value proposition.

  • Presenting the total project cost spent to date compared to the budget.

Question 3 of 15

A project manager is reviewing the financial status of a project. The Estimate at Completion (EAC) is $250,000, and the Actual Cost (AC) to date is $150,000. What is the Estimate to Complete (ETC) for this project?

  • $100,000

  • $250,000

  • $400,000

  • $150,000

Question 4 of 15

A project manager should rely solely on formal performance reviews to support and ensure task accountability among team members, as informal check-ins can lead to inconsistencies in how accountability is enforced.

  • True

  • False

Question 5 of 15

Data analysis in project management should focus only on quantitative data to ensure objectivity in decision-making.

  • False

  • True

Question 6 of 15

What practice is foundational in agile methodologies for a team to embrace continuous improvement?

  • Fixed scope planning

  • Retrospectives

  • Documentation of processes

  • Change requests

Question 7 of 15

In PERT analysis, if the pessimistic estimate for an activity is 25 days and the optimistic estimate is 13 days, the standard deviation is 3 days.

  • False

  • True

Question 8 of 15

Which technique involves consulting with and obtaining guidance from project management and subject matter experts to make informed decisions regarding risk management?

  • Monte Carlo Simulation

  • Qualitative Risk Analysis

  • Expert Judgment

  • Risk Audit

Question 9 of 15

A risk with a probability of 0.3 and an impact of 0.5 has a higher risk score than a risk with a probability of 0.6 and an impact of 0.2.

  • False

  • True

Question 10 of 15

What tool is used in project risk management to record the details of individual project risks, including their descriptions, causes, and how they affect the project?

  • Risk Audit Report

  • Risk Breakdown Structure

  • Risk Register

  • Risk Matrix

Question 11 of 15

When determining a project execution strategy, the consideration of contracting options is exclusively the responsibility of the project's procurement team, without the need for input from the project manager or other stakeholders.

  • False

  • True

Question 12 of 15

During the process of closing procurements, one of the steps involves reviewing all documents to ensure that each contract is settled and closed out. Which of the following actions is most appropriate when closing project procurements?

  • Conduct a final team meeting to release all project resources.

  • Prepare and distribute the final project report to all stakeholders.

  • Collect procurement documentation and ensure that it is complete, indexed, and filed.

  • Update the risk register with new risks encountered during contract execution.

Question 13 of 15

What is the process of organizing and ranking the project requirements to ensure that project efforts focus on the most critical needs?

  • Executing deliverables

  • Decomposing work packages

  • Prioritizing requirements

  • Mapping stakeholders

Question 14 of 15

What is the primary purpose of creating a Work Breakdown Structure (WBS) in project management?

  • To create a timeline for project deliverables and milestones

  • To establish communication protocols for the project team

  • To break down the project into smaller, more manageable components

  • To sequence the project tasks and establish dependencies

Question 15 of 15

What is the primary purpose of appraising stakeholder skills during the initial phase of building a team?

  • Align stakeholders with roles suited to their skills enhancing project efficiency.

  • Predict the overall success of the project at an early stage.

  • Encourage a competitive atmosphere among stakeholders.

  • Assign appropriate security levels and clearance to stakeholders.