00:15:00

Free PMI Project Management Professional Practice Test

Prepare for the PMI Project Management Professional exam with this free practice test. Randomly generated and customizable, this test allows you to choose the number of questions.

  • Questions: 15
  • Time: 15 minutes (60 seconds per question)
  • Included Objectives:
    • People
    • Process
    • Business Environment
    • Agile
    • Waterfall
Question 1 of 15

In the context of a Waterfall project, a project manager is reassessing the stakeholder engagement plan mid-project due to newly identified risks and stakeholders. Which of the following techniques should the project manager prioritize to reassess current support and devise appropriate strategies for enhanced stakeholder engagement?

  • Perform a stakeholder analysis to identify stakeholders' needs, expectations, and potential impact on the project.

  • Focus on stakeholder expectations without consideration of the newly identified risks and changes in stakeholder dynamics.

  • Reduce project communication to a limited number of key stakeholders to streamline decision making.

  • Delegate to a newly formed team who will focus on stakeholder engagement.

Question 2 of 15

You are managing a software development project and discover that a key team member has been reassigned to another high-priority project, leaving your project understaffed. What is the best approach to address this issue?

  • Assess the impact of the resource loss and adjust the project plan accordingly

  • Delay the project until a replacement can be found

  • Proceed with the project as planned using the budget contingency to pay for extra hours

  • Escalate the issue to senior management and request a replacement team member

Question 3 of 15

A project manager is working on a project with 8 stakeholders. How many potential communication channels exist in this project?

  • 16

  • 28

  • 64

  • 56

Question 4 of 15

A project manager is reviewing the project's performance and needs to calculate the Estimate at Completion (EAC). The project has a Budget at Completion (BAC) of $500,000, and the current Cost Performance Index (CPI) is 0.8. Which of the following represents the most likely EAC assuming the current performance trend continues?

  • $400,000

  • $500,000

  • $625,000

  • $550,000

Question 5 of 15

As a project manager, you recognize the importance of maintaining accessible and current project artifacts to support informed decision-making. Which of the following actions would best ensure the continual effectiveness of artifact management?

  • Use an automated version control system notifications to alert stakeholders when artifacts have been updated.

  • Update project artifacts when major project milestones are reached or when significant changes occur.

  • Wait for team members or stakeholders to request updates to project artifacts before making any changes.

  • Conduct regularly scheduled reviews of project artifacts with relevant stakeholders to discuss updates and collect feedback.

Question 6 of 15

You are managing a project that has a diverse group of stakeholders including off-site team members, executive sponsors, and an external regulatory agency. During the planning stage, you aim to determine the most effective way of sharing the project's status updates. Which of the following communication methods is most suitable for providing detailed project updates to all stakeholders?

  • Brief text messages after each project milestone is completed to keep everyone informed

  • Regularly scheduled, detailed email updates with attached reports and analyses

  • Annual formal meetings to review the overall performance and major milestones achieved

  • Real-time dashboards providing key performance indicators and progress metrics

Question 7 of 15

A project manager is working on a software development project in the healthcare sector, which requires adherence to strict data protection regulations. The project manager needs to report on the project’s compliance status in the upcoming steering committee meeting. Which of the following would be the most effective method for measuring the project's compliance?

  • Evaluating the need to expand original project deadlines.

  • Using compliance metrics specific to healthcare data protection standards.

  • Conducting client satisfaction surveys focusing on data security.

  • Collecting general feedback on project performance from team members.

Question 8 of 15

In the final stages of a crucial software project, your team has developed a complex application. Before transitioning the application to the operations team, which of these activities is paramount to guarantee that the new system will be managed effectively and in accordance with the project's goals?

  • Compile and present customer feedback on the application to the operations team.

  • Obtain formal stakeholder sign-off indicating that the project deliverables meet the business needs.

  • Facilitate a detailed knowledge transfer session, including hands-on training with the operations team.

  • Conduct an operational readiness review to measure system performance against project objectives.

Question 9 of 15

A project manager is leading a virtual team with members from various countries. One team member consistently misses deadlines and appears disengaged during video conferences. Which of the following actions should the project manager take first to address this issue?

  • Set clear expectations for all team members regarding deadlines and participation

  • Discuss the issue with the entire team during the next video conference

  • Schedule a one-on-one meeting with the team member to discuss their challenges and cultural background

  • Provide cultural sensitivity training to the entire team

Question 10 of 15

As a project manager, you have identified a stakeholder who has high influence over project outcomes but low interest in the day-to-day operations of the project. Which of the following actions would be most appropriate to manage this stakeholder?

  • Keep them informed through periodic high-level updates about project progress

  • Involve them in the decision-making process for day-to-day operations of the project

  • Exclude them from communications and updates, as they do not have a high interest in the project

  • Provide them with frequent, detailed communications to ensure they are fully informed

Question 11 of 15

During the execution of a project to develop a new software product, the project team delivers functional increments to the client for feedback. However, the client's priorities shift, and certain features originally planned are no longer critical for their operation. How should the project manager ensure that the project continues to deliver business value?

  • Delay the project to reassess its viability in light of the client's shifted priorities before making any changes.

  • Realign the project scope and activities with the client's new priorities to ensure continued delivery of valuable features.

  • Insist on delivering the project according to the initial agreement to avoid the complexities of changing the project scope.

  • Conduct a cost-benefit analysis based on the original project requirements to determine if the planned features should still be developed.

Question 12 of 15

A project manager has identified and categorized the project stakeholders. Which of the following actions should the project manager take next to ensure effective stakeholder engagement?

  • Communicate project updates to all stakeholders regularly

  • Assign responsibilities to each stakeholder based on their category

  • Develop a stakeholder engagement strategy based on the categorization

  • Execute stakeholder engagement activities without a formal strategy

Question 13 of 15

On a project with a Budget at Completion (BAC) of $500,000, the project team has planned to complete 45% of the work by the end of the third month. What is the Planned Value (PV) at the end of the third month?

  • $275,000

  • $250,000

  • $200,000

  • $225,000

Question 14 of 15

You are managing a complex project with a large, cross-functional team. Which of the following actions would be the BEST approach to ensure that project information is maintained accurately and is readily accessible to all stakeholders?

  • Keep paper-based documentation in a centralized office location for team members to access and make updates as needed.

  • Distribute updated project documents to team members via email at the end of each week.

  • Maintain updated project documents in a shared network folder and rely on team members to check this folder for the latest updates before starting their work.

  • Implement a centralized, integrated project management tool with version history and access control features, and establish a routine for regular updates by team leads.

Question 15 of 15

During a software development project, a new government regulation has been introduced, requiring additional data security measures. The Project Manager must adapt the project scope to accommodate these changes. Which of the following is the best option to manage the impact on the project's schedule and costs?

  • Increase the project budget to cover additional costs.

  • Conduct a revised cost-benefit analysis to assess the financial impact and adjust the timeline accordingly.

  • Limit the scope of existing project features to accommodate the new security changes within the current budget.

  • Extend the project timeline by estimating the time required for implementing new security measures.