CompTIA Project+ Practice Test (PK0-005)

Use the form below to configure your CompTIA Project+ Practice Test (PK0-005). The practice test can be configured to only include certain exam objectives and domains. You can choose between 5-100 questions and set a time limit.

Logo for CompTIA Project+ PK0-005 (V5)
Questions
Number of questions in the practice test
Free users are limited to 20 questions, upgrade to unlimited
Seconds Per Question
Determines how long you have to finish the practice test
Exam Objectives
Which exam objectives should be included in the practice test

CompTIA Project+ PK0-005 (V5) Information

The CompTIA Project+ certification is a globally recognized credential designed for professionals who manage small to medium-sized projects. Unlike more specialized project management certifications, Project+ provides a broad foundation, making it an ideal starting point for individuals who are new to project management or who manage projects alongside other job responsibilities. It covers essential concepts such as project life cycles, roles and responsibilities, communication strategies, and risk management. Because it does not require extensive prior experience or prerequisites, it is often seen as a practical alternative to more complex certifications like the PMP, offering a straightforward way for professionals to validate their project management knowledge.

One of the key advantages of CompTIA Project+ is its flexibility across industries. While many project management certifications are heavily focused on IT, Project+ applies to a wide range of business environments, including healthcare, finance, and manufacturing. This makes it especially useful for professionals who may not be strictly in the IT field but still need to understand and manage projects effectively. Employers value Project+ because it demonstrates a candidate’s ability to lead projects, manage resources, and ensure that deliverables meet business objectives. Additionally, it helps bridge the gap between technical teams and stakeholders, fostering better communication and coordination throughout a project's life cycle.

For those looking to advance their careers, CompTIA Project+ serves as a valuable stepping stone to more advanced project management certifications. It provides a solid understanding of fundamental project management principles, which can be built upon with further training and experience. Many professionals who earn Project+ go on to pursue certifications like PMP or PRINCE2, leveraging their foundational knowledge to handle more complex projects. Furthermore, because CompTIA certifications are vendor-neutral, Project+ holders are not tied to any specific project management methodology, giving them the flexibility to adapt to different organizational needs. With a growing emphasis on project-based work across industries, earning Project+ can provide professionals with a competitive edge in the job market.

CompTIA Project+ PK0-005 (V5) Logo
  • Free CompTIA Project+ PK0-005 (V5) Practice Test

  • 20 Questions
  • Unlimited
  • Project Management Concepts
    Project Life Cycle Phases
    Tools and Documentation
    Basics of IT and Governance

Free Preview

This test is a free preview, no account required.
Subscribe to unlock all content, keep track of your scores, and access AI features!

Question 1 of 20

A project manager needs to determine the sequence of activities and identify task dependencies to calculate the critical path of the project. Which of the following tools would BEST help achieve this goal?

  • Gantt chart

  • Milestone chart

  • Budget burndown chart

  • Project network diagram

Question 2 of 20

A project manager is overseeing a project that involves deploying wireless networking equipment in multiple facilities. To ensure compliance with local regulations, which of the following should the project manager prioritize?

  • Verify equipment complies with regional radio frequency regulations.

  • Ensure equipment is purchased from preferred vendors.

  • Select equipment based on cost savings.

  • Rely on the network engineers to handle any compliance issues.

Question 3 of 20

What is the primary purpose of developing a business case during the discovery/concept preparation phase of a project?

  • To track the day-to-day execution of tasks against the project plan.

  • To create a detailed project schedule and work breakdown structure (WBS).

  • To formally close out vendor contracts and release project resources.

  • To justify the project's initiation by evaluating its benefits, costs, and risks.

Question 4 of 20

A project manager needs to determine the necessary steps to transition from the organization's existing operations to the improved operations envisioned by the project. Which of the following should the project manager perform to identify the required changes?

  • Develop a project charter

  • Perform a needs assessment

  • Create a stakeholder register

  • Conduct a gap analysis

Question 5 of 20

A project manager needs to create a visual representation of the project schedule. The tool must display the start and end dates for all tasks, show the duration of each task as a horizontal bar, and illustrate the dependencies between tasks. Which of the following is the BEST tool for this purpose?

  • Fishbone diagram

  • Gantt chart

  • Budget burndown chart

  • Risk register

Question 6 of 20

Which chart is used to display key deliverables or events in a project timeline without detailing task durations?

  • Milestone chart

  • Fishbone diagram

  • Gantt chart

  • Project network diagram

Question 7 of 20

A project manager is leading a critical project that is experiencing significant issues. What approach should the project manager take to maintain the company's brand value?

  • Manage project setbacks discretely to minimize impact.

  • Communicate project progress regularly to stakeholders.

  • Align project outcomes with budget and schedule objectives.

  • Prioritize project timeline without sacrificing quality.

Question 8 of 20

A project manager is leading the development of a new software product. During a planning meeting, a stakeholder raises a concern that the proposed marketing strategy might conflict with the company's established, family-friendly brand image. What is the project manager's MOST appropriate response to this concern?

  • Continue with the project as planned, assuming that senior management is solely responsible for brand strategy.

  • Inform the stakeholder that brand image is outside the scope of the software development project.

  • Acknowledge the concern and facilitate a discussion to align the project's marketing with company brand values.

  • Delegate all responsibility for brand alignment to the marketing department and proceed with the technical tasks.

Question 9 of 20

A company must choose between two projects. Project Alpha will cost $200,000 and is expected to generate $300,000 in revenue. Project Beta will cost $150,000 and is expected to generate $250,000 in revenue. Which project provides a higher percentage return on the initial investment?

  • Cannot determine from the information given

  • Project Alpha provides a higher percentage return

  • Both projects have the same percentage return

  • Project Beta provides a higher percentage return

Question 10 of 20

A project team is having difficulty understanding the sequence of activities and their durations within a project. The project manager decides to provide a visual representation that shows tasks over time, including their start and end dates and how they overlap. Which of the following tools should the project manager use to assist the team?

  • Risk report

  • Issue log

  • Gantt chart

  • Fishbone diagram

Question 11 of 20

A project manager is developing a business case for a new data center. The initial budget includes costs for purchasing servers, networking hardware, and cooling systems. These are long-term assets that the company will own. How should the project manager categorize these one-time, upfront costs?

  • Capital Expenses

  • Administrative Expenses

  • Operational Expenses

  • Variable Expenses

Question 12 of 20

While executing a software rollout project, the team encounters unexpected server outages and a critical vendor shipment delay. The project manager needs a single document to log each problem, assign an owner, set a due date, and track resolution status throughout the lifecycle. Which project management document should the manager update?

  • Change log

  • Project dashboard

  • Risk register

  • Issue log

Question 13 of 20

A project manager is planning a project with tasks that have uncertain durations. The manager wants to use a tool that allows for estimating task durations based on weighted averages of different time estimates to better plan the project schedule. Which project management tool should the manager use?

  • Critical Path Method diagram

  • PERT chart

  • Milestone chart

  • Gantt chart

Question 14 of 20

A project manager wants to engage suppliers who have been evaluated and approved before the project begins to ensure they meet specific criteria. What type of suppliers are these?

  • Prequalified vendors

  • Certified vendors

  • Single-source vendors

  • Preferred vendors

Question 15 of 20

As a project manager at TechNova Inc., you are leading a project to develop a new software application. Midway through the project, a team member suggests adding a feature that could significantly increase customer engagement but might compromise user privacy. Which action should you take to ensure your project aligns with the organization's principles?

  • Reject the suggestion to avoid risks to user privacy.

  • Implement the feature to boost customer engagement.

  • Evaluate the suggestion against the company's values and consult the mission statement before deciding.

  • Forward the suggestion to the marketing department for approval.

Question 16 of 20

As a project manager overseeing a project with a strict budget, you need to monitor and display the amount of budget consumed versus the amount remaining over time to ensure the project stays within financial constraints. Which tracking chart would be most appropriate for this purpose?

  • Budget burndown chart

  • Milestone chart

  • PERT chart

  • Gantt chart

Question 17 of 20

During the discovery phase of an IT infrastructure-upgrade project, you learn that the customer already has active contracts for hardware maintenance and software licensing covering some components you intend to replace. Which action should you take to ensure these agreements are properly handled in your project plan?

  • Defer consideration of the existing contracts until the execution phase to avoid delaying the planning timeline

  • Conduct a detailed contract analysis with procurement and legal to map obligations, constraints, and dependencies into the project scope, schedule, and risk register

  • Proceed with planning as usual and assume the project sponsor will address any conflicts that arise from the contracts

  • Request that procurement terminate the existing contracts and issue new agreements that align with the project's requirements

Question 18 of 20

A company is launching a new project and has already selected the recipient of the project's deliverables before initiation. What is this scenario called?

  • Predetermined client

  • Open procurement

  • Prequalified vendor

  • Potential client

Question 19 of 20

A project manager is overseeing the construction of a new data center. To align with the company's ESG goals, they must select an action that BEST minimizes the project's long-term environmental impact. Which of the following actions is the MOST effective?

  • Develop a green space with native plants on the property surrounding the facility.

  • Source all construction materials from local suppliers to reduce transportation emissions.

  • Implement a comprehensive recycling program for waste generated during the construction phase.

  • Design the facility to use renewable energy sources and energy-efficient cooling systems.

Question 20 of 20

A project manager needs a visual schedule that lists each activity on the vertical axis and places horizontal bars across a calendar-style time scale to indicate when every task starts and finishes. The same chart must also reveal which activities are dependent on others, so the manager can see at a glance which tasks can overlap and which must wait for predecessors to complete. Which type of chart should the project manager create?

  • Gantt chart

  • Milestone chart

  • PERT chart

  • Budget burndown chart