CompTIA Project+ Practice Test (PK0-005)
Use the form below to configure your CompTIA Project+ Practice Test (PK0-005). The practice test can be configured to only include certain exam objectives and domains. You can choose between 5-90 questions and set a time limit.

CompTIA Project+ PK0-005 Information
The CompTIA Project+ certification is a globally recognized credential designed for professionals who manage small to medium-sized projects. Unlike more specialized project management certifications, Project+ provides a broad foundation, making it an ideal starting point for individuals who are new to project management or who manage projects alongside other job responsibilities. It covers essential concepts such as project life cycles, roles and responsibilities, communication strategies, and risk management. Because it does not require extensive prior experience or prerequisites, it is often seen as a practical alternative to more complex certifications like the PMP, offering a straightforward way for professionals to validate their project management knowledge.
One of the key advantages of CompTIA Project+ is its flexibility across industries. While many project management certifications are heavily focused on IT, Project+ applies to a wide range of business environments, including healthcare, finance, and manufacturing. This makes it especially useful for professionals who may not be strictly in the IT field but still need to understand and manage projects effectively. Employers value Project+ because it demonstrates a candidate’s ability to lead projects, manage resources, and ensure that deliverables meet business objectives. Additionally, it helps bridge the gap between technical teams and stakeholders, fostering better communication and coordination throughout a project's life cycle.
For those looking to advance their careers, CompTIA Project+ serves as a valuable stepping stone to more advanced project management certifications. It provides a solid understanding of fundamental project management principles, which can be built upon with further training and experience. Many professionals who earn Project+ go on to pursue certifications like PMP or PRINCE2, leveraging their foundational knowledge to handle more complex projects. Furthermore, because CompTIA certifications are vendor-neutral, Project+ holders are not tied to any specific project management methodology, giving them the flexibility to adapt to different organizational needs. With a growing emphasis on project-based work across industries, earning Project+ can provide professionals with a competitive edge in the job market.
Scroll down to see your responses and detailed results
Free CompTIA Project+ PK0-005 Practice Test
Press start when you are ready, or press Change to modify any settings for the practice test.
- Questions: 15
- Time: Unlimited
- Included Topics:Project Management ConceptsProject Life Cycle PhasesTools and DocumentationBasics of IT and Governance
A project manager plans to set up routine sprint reviews and retrospectives to promote continuous improvement and team collaboration. Which project planning activity does this represent?
Establishing cadences
Developing a communication plan
Assigning project resources
Developing a project schedule
Answer Description
Establishing cadences involves scheduling routine activities like sprint reviews and retrospectives to create a consistent rhythm in the project workflow. This helps the team regularly assess progress, address issues, and enhance collaboration. Developing a project schedule outlines the sequence and timing of tasks but doesn't necessarily include setting up recurring events for team evaluation. Developing a communication plan defines how information will be shared among stakeholders but doesn't schedule regular collaborative activities. Assigning project resources involves allocating team members to tasks, not organizing routine team meetings.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are sprint reviews and retrospectives?
What does establishing cadences mean in project management?
How does a communication plan differ from establishing cadences?
During the planning of a project, Mike discovers an unexpected opportunity to significantly reduce costs by adopting a new technology that is not yet widely used. He decides to adjust the project plan to incorporate this technology in order to gain the cost benefits.
Which positive risk response strategy is Mike utilizing?
Mitigate
Accept
Enhance
Exploit
Answer Description
Mike is employing the Exploit risk response strategy. Exploiting a positive risk involves taking proactive steps to ensure that the opportunity is realized and that the organization benefits from it. By adjusting the project plan to adopt the new technology and directly gain cost reductions, Mike is seizing the opportunity.
The Enhance strategy aims to increase the probability or impact of an opportunity but does not guarantee it, whereas Exploit takes definitive actions to ensure the opportunity occurs. Accept means acknowledging the opportunity but not taking any action unless it happens on its own, which is not the case here. Mitigate is a response strategy for negative risks (threats), aiming to reduce their impact or likelihood and is not applicable to positive risks.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does it mean to exploit a risk in project management?
Can you explain what the other risk response strategies (Enhance, Accept, Mitigate) involve?
Why is it important to have a positive risk response strategy in project management?
In agile development, what do story points help a team understand about a user story?
The relative size or complexity of the user story
The time required to complete the user story
The order in which the user stories should be completed
The cost associated with implementing the user story
Answer Description
Story points represent the relative size or complexity of a user story, helping the team estimate the effort required to implement it. Unlike time estimates, story points focus on how challenging a task is compared to others. This aids in planning and forecasting work during sprint planning. The other options are incorrect because story points do not indicate the time required (option A), the completion order (option C), or the cost (option D) of the user story.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are story points in agile development?
How do teams determine the size or complexity of a user story?
Why is it important to distinguish between time estimates and story points?
A project manager is overseeing a software development project and wants to adopt a methodology that enhances collaboration between developers and IT operations to automate and integrate their processes. Which of the following methodologies should the project manager choose?
Kanban
DevOps
Waterfall
PRINCE2
Answer Description
DevOps is a methodology that focuses on improving collaboration between development (Dev) and operations (Ops) teams. It aims to automate and integrate processes to accelerate software delivery with high quality. The other methodologies do not specifically target the integration of development and operations teams as a primary goal.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the main principles of DevOps?
How does DevOps differ from traditional project management methodologies?
Can you explain what CI/CD means in DevOps?
Which type of diagram helps identify potential causes of a problem by categorizing them into branches?
Pareto chart
Fishbone diagram
Histogram
Scatter diagram
Answer Description
A Fishbone diagram, also known as an Ishikawa diagram, helps identify potential causes of a problem by organizing them into branches that represent different categories of potential causes. This visual tool enables project managers to systematically explore all possible causes of an issue, facilitating root cause analysis. The other options serve different purposes: a Scatter diagram shows relationships between two variables; a Pareto chart ranks causes by frequency or impact; and a Histogram displays the distribution of numerical data.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the main components of a Fishbone diagram?
How is a Fishbone diagram different from a Pareto chart?
Can you explain the process of creating a Fishbone diagram?
You are managing a project to develop a new mobile application. You need to collect in-depth feedback on the app's user interface from a select group of target users to improve usability. Which meeting type should you arrange to achieve this objective?
Demonstrations/presentations
Workshops
Focus groups
Stand-ups
Answer Description
Arranging a focus group is the most appropriate choice in this scenario. Focus groups are designed to gather detailed insights and feedback from a specific group of people about a particular topic or product. They allow for open discussions where participants can share their experiences and opinions, providing valuable qualitative data to improve the application's user interface.
Workshops are collaborative sessions aimed at creating or developing ideas or solutions, but they are not specifically focused on gathering user feedback. Demonstrations/presentations are primarily used to showcase a product or feature to an audience, with limited interaction and feedback. Stand-ups are brief meetings used for status updates within a team and are not suitable for collecting in-depth user feedback.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a focus group and how is it used in project management?
What are the advantages of using focus groups over other feedback methods?
What alternative meeting types could be considered for gathering feedback and how do they differ from focus groups?
During the project planning phase, organizing activities such as operational training, go-live preparations, and handoff procedures is part of developing which plan?
Risk management plan
Quality assurance plan
Transition plan
Communication plan
Answer Description
Developing a transition plan involves planning activities that ensure a smooth transition of the project's deliverables into operational use. This includes organizing operational training for users, preparing for the go-live date, and establishing handoff procedures to the operational team. These activities are essential to effectively move from the project phase to ongoing operations.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a transition plan in project management?
Why is operational training important during the transition phase?
What are handoff procedures and why are they necessary?
During a mobile app development project, a stakeholder requests a new feature that was not included in the original project scope. What should the project manager do first in response to this request?
Discuss the potential inclusion of the feature with the project team
Document the change request and conduct a preliminary review
Assess the necessity of the request and decide on its priority
Implement the new feature to accommodate the stakeholder's needs
Answer Description
The project manager should first document the change request and conduct a preliminary review. This initiates the formal change control process, ensuring that any potential impacts on the project's scope, schedule, and budget are assessed before decisions are made. Assessing the necessity or discussing the request without documentation overlooks the structured approach needed for change management. Implementing the change immediately can lead to unmanaged scope creep.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a change request in project management?
What is the change control process?
What is scope creep and how can it be managed?
A project manager needs to create a visual presentation to communicate the project milestones to stakeholders during a meeting. Which type of software is most appropriate for this purpose?
Presentation software
Ticketing/case management system
Word processing software
Spreadsheet software
Answer Description
Presentation software is designed for creating slideshows and visual presentations, making it ideal for communicating project milestones during meetings. While spreadsheet software is great for numerical data and calculations, and word processing software is suited for text documents, they are not as effective for creating engaging visual presentations. A ticketing/case management system is used for tracking issues and tasks, not for creating presentations.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are some examples of popular presentation software?
How can I make my presentation more engaging?
What is the role of project milestones in project management?
A project manager is planning a new software development project and is deciding between Agile and Waterfall methodologies. They need to assemble their project team. Which of the following best describes how team size typically differs between Agile and Waterfall approaches?
Waterfall methodologies require smaller teams due to their phased approach, while Agile supports larger teams for iterative development.
Team size is irrelevant when choosing between Agile and Waterfall methodologies.
Agile methodologies typically involve smaller teams for better collaboration, whereas Waterfall can handle larger team sizes.
Both Agile and Waterfall methodologies recommend the same team size for optimal performance.
Answer Description
Agile methodologies favor smaller, cross-functional teams, usually consisting of 5-9 members, to enhance collaboration and adaptability. Smaller teams are more effective in Agile environments where rapid communication and flexibility are essential. In contrast, Waterfall methodologies can accommodate larger teams due to their structured and sequential nature, where tasks are divided among specialists working in defined phases. Therefore, understanding that Agile prefers smaller teams while Waterfall can function with larger teams is key.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the main characteristics of Agile methodologies?
Why does Agile favor smaller teams compared to Waterfall?
Can Waterfall methodologies be effective with smaller teams?
As a project manager for a software development project, you are determining the order of tasks in your schedule. Task A is 'Develop User Interface', and Task B is 'Perform User Acceptance Testing'. Testing cannot begin until development is fully completed. Which of the following best describes the appropriate logical link between these two tasks?
Start-to-Finish (SF)
Finish-to-Start (FS)
Start-to-Start (SS)
Finish-to-Finish (FF)
Answer Description
The Finish-to-Start (FS) relationship is appropriate because Task B ('Perform User Acceptance Testing') cannot start until Task A ('Develop User Interface') has finished. In an FS relationship, the successor task begins only after the predecessor task has completed, which accurately reflects the sequence where testing follows the completion of development. The Start-to-Start (SS) relationship would mean both tasks begin at the same time, which doesn't fit since testing depends on development completion. Finish-to-Finish (FF) implies both tasks finish simultaneously, which isn't the case here. Start-to-Finish (SF) is a less common relationship where the successor task cannot finish until the predecessor task starts, which does not apply to this scenario.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does Finish-to-Start (FS) mean in project management?
What are the other types of task dependencies in project management?
Why is user acceptance testing important in software development?
As a project manager overseeing the implementation of a new database system, which consideration is most important to ensure data compliance and security during the project?
Ensuring the database integrates seamlessly with current applications
Providing training sessions for the project team on database use
Optimizing the database for maximum query performance
Verifying that the database meets data classification and privacy regulations
Answer Description
Ensuring that the database complies with data classification and privacy regulations is crucial. This includes implementing necessary access controls and encryption methods to protect sensitive information such as PII and PHI. While performance optimization, staff training, and integration with existing systems are important, they do not directly address compliance and security requirements that are essential for protecting data and meeting legal obligations.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are data classification and privacy regulations?
What are some examples of necessary access controls for a database?
Why is encryption important for database security?
As a project manager, you realize that some of your project's essential software tools require maintenance to continue functioning effectively during the project. What is the BEST course of action to address this need while minimizing impact on project progress?
Assign maintenance tasks to team members within current plans.
Delay maintenance until after project completion.
Schedule routine maintenance in consideration of the project timeline.
Consider replacing tools with alternatives that require less maintenance.
Answer Description
Scheduling routine maintenance in consideration of the project timeline is the best approach because it allows for necessary upkeep without causing significant disruptions. By planning maintenance during less critical periods, the tools remain functional, and the project's progress is maintained. Delaying maintenance until after project completion risks tool failure or decreased performance, which can adversely affect the project. Assigning maintenance tasks to team members within current plans may overburden them and detract from their primary responsibilities. Considering replacing tools with alternatives that require less maintenance introduces new variables, such as training needs and compatibility issues, potentially leading to delays and increased costs.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does it mean to schedule routine maintenance in consideration of the project timeline?
Why is delaying maintenance until after project completion considered a poor choice?
What are some potential issues with replacing tools with alternatives that require less maintenance?
Which type of testing involves running a set of basic tests on a software application to ensure that the most crucial functions work after a new build or update?
Smoke testing
Regression testing
Stress testing
Unit testing
Answer Description
Smoke testing involves executing a suite of tests that check the essential functionalities of an application after a new build or update. It helps determine if the critical features are working properly and if the build is stable enough for further, more detailed testing. Unlike regression testing, which retests application functionality after changes to ensure no new bugs were introduced, smoke testing focuses on the initial assessment of the application's core functions. Unit testing tests individual components in isolation, and stress testing evaluates the application's performance under extreme conditions.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the main objectives of smoke testing?
How does smoke testing differ from other testing types like regression testing?
Can you explain what unit testing and stress testing are?
A project manager needs to visually represent the hierarchy and communication pathways among project team members. Which tool should the manager use?
Work breakdown structure
Gantt chart
Risk breakdown structure
Project organizational chart
Answer Description
The project organizational chart is used to visually depict the project's organizational structure, including roles, responsibilities, and reporting relationships. It helps team members understand who reports to whom and how information flows within the project. A Gantt chart is used for scheduling project tasks over time. A risk breakdown structure categorizes potential project risks. A work breakdown structure decomposes the project scope into manageable sections.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a project organizational chart?
What is the difference between a Gantt chart and an organizational chart?
How does understanding the project hierarchy benefit team communication?
Woo!
Looks like that's it! You can go back and review your answers or click the button below to grade your test.