CompTIA Security+ SY0-701 Practice Question
Crucial Technologies determined through a risk analysis the level of risk they are willing to accept before measures are needed to reduce the risk. This level of risk is called what?
Risk awareness
Residual Risk
Risk register
Risk appetite