CompTIA Security+ SY0-701 Practice Question
A company's primary data center located in a hurricane-prone area has just experienced a significant storm, leading to a sustained power outage and compromised physical infrastructure. The company relies on a combination of on-site back-ups and replication to an off-site data center for their disaster recovery strategy. Given these details, which of the following would BEST ensure the continuation of business operations during this event?
Implementing incremental backups until the primary data center is restored and operational.
Waiting until the primary data center is restored to resume critical business operations.
Activating the business continuity plan which includes failing over to the off-site data center.
Restoring operations from onsite backups as soon as connectivity is re-established.