CompTIA Server+ SK0-005 Practice Question
During a data-center consolidation project, you submit a Request for Change (RFC) to permanently retire a four-year-old database server. The draft change already lists the maintenance window, the back-out procedure, secure disk-wiping steps, and the vendor's disposal method. During its review, the Change Advisory Board (CAB) says one task related to configuration management is still missing and must be added before the change can be approved. Which task should you insert into the implementation plan?
Mark the server's configuration-item record as Retired in the CMDB and update or remove its dependency mappings.
Instruct the finance department to accelerate depreciation of the asset in the next accounting cycle.
Schedule a post-implementation review meeting with the CAB and key service owners following the change window.
Arrange for the e-waste recycler to provide a certificate of destruction before the maintenance window starts.