AWS Certified Solutions Architect Professional SAP-C02 Practice Question
A financial services company is planning to migrate its on-premises Oracle data warehouse to Amazon Redshift. The source database contains a significant number of custom stored procedures, user-defined functions, and complex views that are critical for business intelligence reporting. A solutions architect needs to provide an accurate estimate of the effort and timeline for the database schema conversion phase of the project. The team will use the AWS Schema Conversion Tool (SCT) as part of the assessment.
What is the most critical output from the AWS SCT that the architect should use to create this effort estimate?
A configuration file for AWS Database Migration Service (DMS) that automates the full load and Change Data Capture (CDC) tasks.
A list of recommended Amazon Redshift node types and cluster configurations based on the source database's performance metrics.
The optimized SQL scripts for the target Amazon Redshift database that are ready for immediate deployment.
The Database Migration Assessment Report, which details the percentage of schema objects that can be automatically converted and highlights those requiring manual intervention.
The correct answer is the Database Migration Assessment Report. The primary purpose of using the AWS Schema Conversion Tool (SCT) in the initial assessment phase of a heterogeneous database migration is to analyze the source schema and produce this report. The report provides a detailed summary of the schema objects, indicating which can be converted automatically to be compatible with the target database (Amazon Redshift, in this case) and, crucially, which objects require manual intervention and remediation. It also includes an estimate of the effort required to convert the objects that cannot be handled automatically. This information is essential for a solutions architect to accurately plan the migration, estimate the manual effort involved, and create a realistic project timeline.
The optimized SQL scripts are a result of the conversion process, not the initial assessment for planning. Furthermore, these scripts are not guaranteed to be ready for immediate deployment and almost always require review and testing, particularly for complex objects that were flagged in the assessment report.
A configuration file for AWS Database Migration Service (DMS) is not a primary output of the SCT assessment. While SCT and DMS work together, with SCT handling schema conversion and DMS handling data replication, the assessment report's purpose is to estimate schema conversion effort, not to configure data movement tasks.
A list of recommended Amazon Redshift node types is not a function of SCT. Sizing a target cluster involves analyzing source database performance metrics, workload patterns, and data volume, which is typically done using other tools and analyses, such as those provided by AWS Migration Hub or a TCO calculator, not SCT.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does the Database Migration Assessment Report include?
Open an interactive chat with Bash
How does AWS Schema Conversion Tool (SCT) handle objects that require manual intervention?
Open an interactive chat with Bash
When should you use SCT instead of AWS Database Migration Service (DMS)?
Open an interactive chat with Bash
AWS Certified Solutions Architect Professional SAP-C02
Accelerate Workload Migration and Modernization
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
IT & Cybersecurity Package Join Premium for Full Access