Project Management Professional Practice Question

Your team is planning the scope for a hybrid project to roll out a new customer self-service portal. During a decomposition workshop, team members propose several techniques to break the work into manageable pieces so that estimates and responsibilities can be assigned. One stakeholder suggests building a detailed Gantt chart at this stage to help everyone visualize the work. According to PMI best practices, which technique mentioned should NOT be used for breaking down the project scope and is therefore better deferred until after scope decomposition is complete?

  • Product backlog

  • User-story mapping

  • Gantt chart

  • Work Breakdown Structure (WBS)

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot