PMI Project Management Professional Practice Question
Your project requires adherence to strict data protection regulations. To ensure ongoing compliance, which method should you primarily implement?
Organize periodic training sessions on compliance standards.
Use standard project management methodologies.
Conduct regular compliance audits.
Enhance system functionalities to ensure compliance.