PMI Project Management Professional Practice Question
Your project is in the deployment phase, and you need to ensure that the benefits derived from the project are being tracked effectively. Which of the following would be the best method to ensure that the project's benefits are continuously measured?
Utilize general project feedback for benefit measurement
Calculate cost savings to track benefits
Use evaluations based on internal positioning of stakeholders
Implement a comprehensive benefits realization plan