Your project is halfway through its development phase when new environmental regulations are introduced, which could potentially affect multiple ongoing tasks. What should be your first step to address this situation?
Postpone tasks that could be affected by the new regulations.
Reassign affected tasks to different team members to avoid project delays.
Inform all stakeholders about the new regulations and their potential impact.
Assess and evaluate the impact of the new regulations on the project scope and backlog.
The correct answer is to assess and evaluate the impact of the new regulations on the project scope and backlog. This approach ensures a thorough understanding of how the changes will affect the project and allows for appropriate adjustments to be planned. While informing the stakeholders is also essential, it comes after evaluating the impact. Postponing tasks or reassigning tasks are reactive strategies that should be based on the initial evaluation.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is it important to assess and evaluate the impact of new regulations first?
Open an interactive chat with Bash
What tools or techniques can be used to evaluate the impact of regulatory changes on a project?
Open an interactive chat with Bash
After evaluating the impact, what steps should be taken to ensure project alignment with new regulations?
Open an interactive chat with Bash
Project Management Professional
Business Environment
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .